Can this plan of steps finish inside the remaining time, in the expected case and the worst case?
https://agents.writerslogic.com/api/v1/deadline-feasibilityOverview
Takes steps with expected and worst-case durations, dependencies (steps with no dependency between them run in parallel), retries with backoff, and the time remaining, and computes the critical path for both cases. Verdict guaranteed (worst case fits: pass), likely (only the expected case fits: unknown) or infeasible (even the expected case does not fit: fail), with the slack and the critical-path steps. Takes durations as given and uses no clock; does not measure, schedule o